DRAFT
TM 5-4210-249-13&P-1
0105
MALFUNCTION
TEST OR INSPECTION
CORRECTIVE ACTION
TFFT02785
Step 11.
Turn battery disconnect switch to ON position (WP 0007). With a test lead set, check
for 22 to 28 VDC between pump house power distribution wire harness wire 2314 (red)
at relay P2 connector, terminal 1 and a known good ground.
If 22 to 28 VDC are not present, replace pump house power distribution wire
harness and block (WP 0457).
Step 12.
With a test lead set, check for 22 to 28 VDC between pump house power distribution
wire harness wire 2314 (red) at relay P2 connector, terminal 4 and a known good
ground.
If 22 to 28 VDC are not present, replace pump house power distribution wire
harness and block (WP 0457).
0105-10