0024 00
2. Remove the fire monitor (figure 1, item 4).
3. Remove and discard the gasket (figure 1, item 5) from the fire monitor flange (figure 1, item 3).
INSTALLATION
1. Thoroughly clean the fire monitor flange (figure 1, item 3).
2. Position a new gasket (figure 1, item 5) on the fire monitor flange (figure 1, item 3).
3. Position the fire monitor (figure 1, item 4) on the valve (figure 1, item 6) and secure it with the four bolts (figure 1,
item 1) and four nuts (figure 1, item 2).
4. Remove the lockouts and tagouts (FM 55-502).
5. Test the fire monitor (WP 0023 00), and observe that the fire monitor operates normally without leakage.
6. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE