4-23. ENGINE COOLER VALVE
This task covers:
a.
Removal
c.
Follow-on Maintenance
b.
Installation
TOOLS REQUIRED
EQUIPMENT CONDITION
Tool Kit, General Mechanics, Automotive
Main Engine Shutdown (see para. 2-12.)
(Appendix B. Section lIl, Item 1)
APU Shutdown (see para. 2-16.)
Gauge Panel Removed (see para. 4-18.)
Batteries Disconnected (see para. 4-114.)
a.
Removal.
(1) Remove set screw (1), and handle (2).
(2) Tag and remove two hoses (6) from valve (5).
NOTE
Before removal, note orientation of valve on panel
to ensure correct operation after replacement.
(3) Remove nut (at, lock washer (4) and valve {51
b. Installation.
(1) Install valve (5) on panel and secure with lock
washer (4) and nut (3).
(2) Install two hoses (6) on valve (5).
(3) Install handle (2) and set screw (1).
c.
Follow-on Maintenance.
(1) Install gauge panel (see para. 4-18).
(2) Connect batteries (see para. 4-114).