DRAFT
TM 5-4210-249-13&P-3
0403
INSTALLATION
1.
Install lightbar flasher unit (16) on personnel cab roof lightbar (2) with two rivets (15).
2.
Install white wire (13) on lightbar flasher unit, terminal 11 (14).
3.
Install white wire (11) on lightbar flasher unit, terminal 10 (12).
4.
Install red wire (9) on lightbar flasher unit, terminal 8 (10).
5.
Install blue wire (7) on lightbar flasher unit, terminal 6 (8).
6.
Install green wire (5) on lightbar flasher unit, terminal 3 (6).
7.
Install red wire (3) on lightbar flasher unit, terminal 2 (4).
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
TFFT03682
NOTE
Lights installed in Step (8) are 3rd and 4th lights from passenger side.
8.
Install two lights (1) on personnel cab roof lightbar (2) (WP 0351).
END OF TASK
FOLLOW-ON MAINTENANCE
Connect batteries (TM 9-2320-325-14&P)
END OF TASK
END OF WORK PACKAGE