5.
Install hose (5) on charge air cooler (6) and intake tube (7) with two clamps (4).
6.
Install ducting (2) on charge air duct (3) with two clamps (1).
NOTE
Use the suggested tension setting for initial tensioning. When belt is installed, run water
pump engine under load for 15 minutes, shut down and readjust belt tension.
Adjust belt tension to within +/- 11 lb-ft (49 N) of recommended tension.
7.
Start pump engine and run under load for 15 minutes.
8.
Shut down engine and readjust belt tension to 67 lb-ft (298 N), as indicated by belt tensioner gauge.
END OF TASK
FOLLOW-ON MAINTENANCE
1.
Close passenger side crew cab access panel (WP 0499)
2.
Close pump operator's panel housing (WP 0325)
3.
Install pump house panel U (WP 0540)
END OF TASK
END OF WORK PACKAGE
0230-4