TM 5-4210-233-14&P-1
5-61. MAIN HYDRAULIC PUMP - Continued
b.
Installation.
(1)
Secure main hydraulic pump (4) to PTO (7) with two mounting washers (6) and bolts (5).
(2)
Install three hydraulic hoses (1, 2 and 3).
c.
Follow-on Maintenance.
(1)
Fill hydraulic oil tank (see para 5-48).
(2)
Connect batteries (see para 4-114).
(3)
Start main engine (see para 2-12) and run aerial functions and check operation of pump and check
for leaks (see para 2-14).
(4)
Tighten connections as needed.
(5)
Shut main engine down (see para 2-12).
(6)
Install curbside operator panel (see para 4-26).
5-353
|