5-54. SWING BRAKE
This task covers:
a.
Removal
c.
Follow-on Maintenance
b.
Installation
TOOLS REQUIRED:
EQUIPMENT CONDITION
Tool Kit, General Mechanics, Automotive
Main Engine Shutdown (see para 2-12.)
(Appendix B, Section III, Item 1)
APU Shutdown (see para 2-16.)
Batteries Disconnected (see para 4-114.)
Ladder Bedded (see para 2-14.)
Swing Motor Removed (see para 5-62.)
a.
Removal
(1) Remove hydraulic hose (1) from swing brake (2).
(2) Plug swing brake port and cap hydraulic hose (1).
(3) Remove two bolts (3).
(4) Remove swing brake (2).
b.
Installation.
(1) Secure swing brake (2) to planetary speed reducer (4) with two bolts (3). Torque bolts to 71-75 lb. ft.
(96-102 N.m).
(2) Secure hydraulic hose (1) to spring brake (2).
c.
Follow-on Maintenance.
(1) Install swing motor (see para 5-62).
(2) Connect batteries (see para 4-114).