TM 9-1240-375-34&P
0010 00
COVER ASSEMBLY
Table 1. Troubleshooting Procedures.
NOTE
The following steps are written and illustrated for the M17/M18 quadrant but also
apply to the M17A1/M18A1 quadrant.
MALFUNCTION
TEST OR INSPECTION
CORRECTIVE ACTION
1
1
1 fc 0 2 7
M17/M17A1 Quadrant
M18/M18A1 Quadrant
WARNING
TRITIUM
GAS (H3)
When maintaining radioactively illuminated fire control equipment, follow radiation
hazard procedures in warning summary.
1. COUNTER WINDOWS (1)
Check for damaged glass or
1. Replace glass if required
ARE FOGGED OR HAVE
defective or missing parts.
2. Replace defective or missing
parts as required and
authorized (WP 0052 00,
3. Purge and charge quadrant
with dry nitrogen
(TM 750-116).
END OF WORK PACKAGE
0010 00-2
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |