TM 55-1925-292-14&P
0035 00
INSTALLATION
1. Fabricate new gaskets from bulk stock using the inlet piping flange (figure 1, item 1) and discharge piping
flange (figure 1, item 7) as templates.
2. Install a new gasket (figure 1, item 4) between the inlet piping flanges (figure 1, item 1).
3. Secure the inlet piping flange (figure 1, item 1) with the eight bolts (figure 1, item 2) and eight nuts (figure 1,
item 3).
4. Install a new gasket (figure 1, item 8) between the discharge piping flanges (figure 1, item 7).
5. Secure the discharge piping flange (figure 1, item 1) with the eight bolts (figure 1, item 5) and eight nuts
(figure 1, item 6).
6. Remove the lockouts and tagouts (FM 55-502).
7. Operate the diesel engine-driven firefighting pump (WP 0005 00) and observe that the pump operates nor-
mally without leakage or unusual noises.
8. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE
0035 00-2
|