TM 55-1925-292-14&P
0033 00
OFF
JCV-PRO-3
ON
1
6
5
4
2
3
Figure 1. Engine Room Water Washdown System Strainer
ASSEMBLY
1. Install the basket (figure 1, item 6) into the strainer assembly (figure 1, item 1).
2. Install a new gasket (figure 1, item 5) and the cover (figure 1, item 4) on the strainer assembly (figure 1,
item 1) and secure the cover with the six nuts (figure 1, item 2) and six flat washers (figure 1, item 3).
3. Remove the lockouts and tagouts (FM 55-502).
4. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE