TM 55-1925-292-14&P
0027 00
INSTALLATION
1. Position the fire and smoke detection panel on the main switchboard and secure it in place with the six bolts
(figure 2, item 2), six nuts (figure 2, item 3), 12 flat washers (figure 2, item 4), and six new lockwashers (figure 2,
item 5).
2. Route and install the electrical wiring (figure 2, item 1) in the fire and smoke detection panel using the labels
from step 1 of Removal as a guide. Remove the labels.
3. Install the inboard 440 volt panel (figure 1, item 5) on the main switchboard (figure 1, item 3) and secure it by
tightening the four captive screws.
4. CLOSE the number 2 generator control panel (figure 1, item 2) and secure it with the two captive screws
(figure 1, item 1).
5. Remove the lockouts and tagouts (FM 55-502) and return the vessel to the desired electrical readiness level.
6. Install all component modules (WP 0026 00).
7. Perform the fire detection system test (WP 0017 00 or WP 0025 00).
8. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE
0027 00-4
|