TM 55-1925-292-14&P
0016 00
3. Loosely install the packing gland nut (figure 7, item 10) into the bonnet (figure 7, item 6).
4. If the valve seat (figure 7, item 7) was removed during Disassembly, install a new valve seat on the stem
(figure 7, item 3).
5. Position a new gasket (figure 7, item 9) on the body (figure 7, item 8).
6. Place the bonnet (figure 7, item 6), shaft (figure 7, item 3), and valve seat (figure 7, item 7) into the body
(figure 7, item 8) as an assembly and secure the bonnet with the four nuts (figure 7, item 4) and four bolts
(figure 7, item 5).
7. Place the handwheel (figure 7, item 2) on the stem (figure 7, item 3) and secure it with the nut (figure 7, item 1).
8. Perform the Typical Flanged Globe Stop Check Valve Installation procedure in this work package.
9. Perform the Follow-On Service procedure at the end of this work package.
FOLLOW-ON SERVICE
1. Remove the lockouts and tagouts (FM 55-502).
2. Pressurize the fire main (WP 0005 00).
3. Check for leaks and proper operation.
4. Return the equipment to the desired readiness condition.
END OF WORK PACKAGE