TM 5-4210-233-14&P-1
5-9. FRONT SUCTION ASSEMBLY
This task covers:
a.
Removal
c.
Follow-on Maintenance
b. Installation
TOOLS REQUIRED
EQUIPMENT CONDITION
Tool Kit, General Mechanics, Automotive
All Piping Drained (see para 2-17.)
(Appendix B, Section III, Item 1)
Main Engine Shutdown (see
para 2-12.)
APU Shutdown (see para 2-16.)
MATERIALS/PARTS REQUIRED
Batteries Disconnected (see para 4-114.)
Pipe Sealant (Item 2, Appendix E)
Curb Side Panel Removed (see para 4-26.)
Multipurpose grease (Item 17, Appendix E)
Tie Straps (Item 33, Appendix E)
a.
Removal.
(1)
See paragraph 4-51 to remove and repair front suction valve. See paragraph 4-54 for removal and
installation of front suction drain valves.
(2)
To remove piping sections remove bolts (1), nuts (2), clamp halves (3) and seals (4) as necessary.
(3)
To remove elbow (5), support piping at front suction valve and remove eight bolts (6).
(4)
To remove long pipe (7) support pipe with suitable blocking and remove clamps (3) as described
above. Remove bolts (8), nuts (9) and flat washers (10 and 11). Remove rubber grommets (12) if
necessary.
(5)
To remove front pipe (13), disconnect tube (14) and remove elbow (15). Remove screws (1 6) and
garnish ring (17). Unscrew strainer (18). Remove nuts (19), washers (20 and 21) and U-bolt (22).
5-35
|