TM 5-4210-233-14&P-1
4-100. TRANSMISSION SHIFT CONTROL-Continued
b. Removal, Transmission Control Cable.
(1) Remove cable (12) from transmission shift control (19) as described in para a. above.
(2) To remove cable from transmission, remove spring clip (20).
(3) Mark location of and remove end fitting (21) from bracket (22).
(4) Remove two nuts (23) and lockwashers (24) from U-bolt (25), and remove cable from bracket (26).
(5) Cut tie straps holding cable (12) to truck.
(6) Remove cable (12) from truck.
c.
Cleaning and Inspection.
(1) Inspect cable for fraying or cracked insulation. If cable is damaged, replace.
(2) Inspect cable for corrosion. Clean corrosion with emery cloth (Item 25, Appendix E). If corrosion
cannot be removed, replace cable assembly.
d. Installation, Transmission Control Cable.
(1) Install end fitting (14) of cable (12) to transmission shift control (19).
(2) Install spring clip (13) in end fitting (14).
(3) Attach cable (12) body to transmission shif control using two nuts (15), lockwashers (16) and
t
screws (17) and clamp (18).
(4) Feed cable through cab console and route to transmission hookup.
(5) Attach cable end fitting (21) to bracket (22) and install spring clip (20).
(6) Install cable (12) to bracket (26) with U-bolt (25) and two nuts (23) and lockwashers (24).
(7) Secure cable to truck with tie straps (Item 33, Appendix E).