|
|
TM 5-4210-233-14&P-1
4-75. WATER TANK LEVEL SENDING UNIT
This task covers:
a. Removal
c. Follow-on Maintenance
b. Installation
TOOLS REQUIRED
EQUIPMENT CONDITION
Tool Kit, General Mechanics, Automotive
Main Engine Shutdown (see para 2-12 .)
(Appendix B, Section III, Item 1) APU Shutdown (see para 2-16 .)
Batteries Disconnected (see para 4-114 .)
MATERIALS PARTS
Gasket (Fig. 44, Appendix F)
a. Removal.
(1) Remove four screws (1) and access panel (2)
from hose bed floor.
(2) Disconnect wiring harness (3).
(3) Remove six screws (4).
(4) Remove sending unit (5) and gasket (6) from
water tank.
(5) Clean water tank gasket surface.
b. Installation.
(1) Install new gasket (6) and sending unit (5).
(2) Secure sending unit with six screws (4).
(3) Connect wiring harness (3).
(4) Install access panel (2) to hose bed floor with
four screws (1).
c.
Follow-on Maintenance.
(1)
Connect batteries (see para 4-
114).
4-304
|
Privacy Statement - Press Release - Copyright Information. - Contact Us |